Solar Subsidy for Apartments and Housing Societies in Siliguri: How Much Can an RWA Get in 2026?
PM Surya Ghar gives housing societies in Siliguri ₹18,000 per kW for common-area solar. See limits, WBSEDCL rules and steps to apply before March 2027.

The short answer
A registered housing society or Resident Welfare Association (RWA) in Siliguri can get PM Surya Ghar central subsidy of ₹18,000 per kW for rooftop solar that powers common facilities, including EV charging, up to 500 kW at 3 kW per house. The money is paid by the Government after installation, not given as a discount.
Can an apartment or housing society in Siliguri get solar subsidy?
Yes. PM Surya Ghar: Muft Bijli Yojana is not only for independent houses. It also gives central financial assistance to Group Housing Societies (GHS) and Resident Welfare Associations (RWA) for a rooftop solar plant that runs common facilities, such as lifts, water pumps, corridor and campus lights, and EV charging points [2]. This matters for Siliguri, Matigara and Bagdogra, where many families now live in apartment complexes and pay a shared common-area electricity bill through maintenance charges. The scheme is growing fast across India: by September 2026 it had covered about 59.5 lakh households and 17.5 GW of residential rooftop capacity [1]. It is scheduled to run until 31 March 2027 [1], so societies that want the subsidy should start planning now.
How much subsidy does a housing society get?
The rate for a GHS or RWA is ₹18,000 per kW for common facilities, for plants up to 500 kW [2]. The cap is worked out at 3 kW per house, and the 500 kW limit includes any rooftop plants already installed by individual residents in the same society [2]. Simple example: a society with 30 flats can count up to 90 kW (30 × 3 kW) toward the subsidy limit. If it installs a 25 kW plant on the common connection, the subsidy works out to 25 × ₹18,000 = ₹4,50,000. This is different from an individual home, which gets ₹30,000 per kW up to 2 kW, ₹18,000 for the third kW, and a maximum of ₹78,000 for 3 kW and above [2]. In every case the subsidy is paid by the Government into the bank account after the plant is installed and inspected. It is not a price discount, and West Bengal does not add any extra state subsidy on top.
How big a solar plant can our society install under WBSEDCL rules?
Two limits apply, and the smaller one decides your size. The first is the subsidy limit above. The second is the WBSEDCL connection limit. Under the WBERC Grid-Interactive Rooftop Solar PV Regulations 2025, net metering is allowed from 1 kW up to 500 kW, or up to the contract demand of that electricity connection, whichever is lower [3]. Contract demand means the load (in kW) that WBSEDCL has sanctioned for your common-area meter. So if your society's common meter has a 25 kW contract demand, the net-metered plant will usually be limited to about 25 kW, even if the subsidy cap is higher. WBSEDCL also checks that total solar on your local feeder or transformer does not cross its capacity [3]. A proper site survey checks your bill, contract demand and roof area together, so the society knows the real size before it votes on a budget.
What happens to extra solar power on weekends or holidays?
With net metering, units your plant sends to the grid are adjusted against units the common meter takes from the grid. Any surplus left at the end of the financial year resets and does not carry forward [3]. That is why the plant should be sized close to what the common area actually uses in a year, not as big as the roof allows. WBERC rules also allow net billing and gross metering, where exported units are valued at a fixed feed-in tariff instead [3]. For the 2025-26 period that rate was ₹4.37 per unit for low and medium voltage connections [3]. For most societies with a steady daytime load from pumps, lifts and lights, net metering is usually the simpler choice, but the right option depends on your bill pattern.
What is the step-by-step process for an RWA in Siliguri?
Step 1: The society's managing committee passes a resolution to go solar and nominates one person to handle the work. Step 2: A free site survey checks the roof (shade from water tanks and nearby towers, roof strength, space for walkways), the last 12 months of common-area bills, and the contract demand. Step 3: The application is filed on the PM Surya Ghar national portal, choosing a registered vendor, and the WBSEDCL application is made. WBSEDCL charges an application fee of ₹1,000 for low and medium voltage connections and ₹5,000 for HV connections [3]. Step 4: WBSEDCL does a technical check. Plants up to 10 kW are approved without a separate feasibility study, while bigger plants need a technical study [4]. Step 5: Installation with DCR (made-in-India) modules, which are needed for subsidy. Step 6: WBSEDCL inspection, net meter installation and commissioning. Step 7: The subsidy claim is processed on the portal and paid to the society's bank account. Timelines depend on WBSEDCL and the portal, so no installer can promise a fixed date.
Why choose a local installer for a housing society project?
A society project has more people, more papers and more roof issues than a single house. A local team can visit more than once, meet the committee, and answer residents' questions in person. Brijstar Green Energy Pvt Ltd is a solar EPC company based in Siliguri and a registered vendor on the PM Surya Ghar national portal for the WBSEDCL area. We file the subsidy application, handle WBSEDCL net metering liaison, and do the design, installation, commissioning and after-sales service. As an authorised channel partner of Tata Power Solar, we can offer Tata Power Solar systems for homes and societies across Siliguri, Matigara, Bagdogra and the rest of North Bengal. Note that PM Surya Ghar subsidy work is done only for properties inside West Bengal under WBSEDCL. To check how much your society can save, book a free site survey with Brijstar — call or WhatsApp +91 99324 08999, or visit brijstar.com.
Common questions
Can a single flat owner in a Siliguri apartment get PM Surya Ghar subsidy alone?
The scheme's society route is for common facilities through the GHS or RWA. A flat owner usually has no separate roof space. If you have your own electricity connection and your own roof area, ask for a site survey and we will check eligibility on the portal.
Does our society need to be registered to apply?
The subsidy is for a Group Housing Society or Resident Welfare Association. Keep your registration papers, committee resolution and common-area electricity bill ready before applying.
Is the ₹18,000 per kW given as a discount on the price?
No. The society pays the full cost to the installer. The Government pays the subsidy into the society's bank account after the plant is installed and inspected.
Can solar power our society's EV charging points?
Yes. EV charging is listed as a common facility for GHS/RWA subsidy under PM Surya Ghar.
What is the last date to get this subsidy?
PM Surya Ghar is scheduled to run until 31 March 2027. Applications take time, so it is safer to start well before the deadline.
Sources and checks
- [1] Business Standard – PM Surya Ghar crosses 17.5 GW; rooftop additions fall for 2nd month (7 Oct 2026)
- [2] District Administration Pune (Govt. of Maharashtra) – PM-Surya Ghar: Muft Bijli Yojana subsidy structure
- [3] WBSEDCL – Procedures-C (2025) for grid-interactive rooftop solar under WBERC Regulations 2025
- [4] Energetica India – WBERC issues Grid-Interactive Rooftop Solar PV Regulations, 2025
Confirm current utility and scheme rules before purchase.